International airlines seek to delay transfer to Long Thành

  • Date modified:8:57 21/11/2026

Thirty-four international airlines have sought to delay transferring their operations from Tân Sơn Nhất to Long Thành until late 2027 or 2028, citing the time needed to prepare aircraft, crews and ground services, according to a report by the Ministry of Construction.

An aerial view of Long Thành International Airport in Đồng Nai Province, about 40km east of HCM City, which is scheduled to begin commercial operations on December 24, 2026. — VNA/VNS Photo

HCM CITY — Thirty-four international airlines have proposed delaying the transfer of their operations from Tân Sơn Nhất International Airport to Long Thành International Airport in Đồng Nai Province until late 2027 or 2028, citing the time needed to prepare aircraft, crews, ground services and other supporting facilities.

According to a report by the Ministry of Construction, 24 airlines proposed moving during the winter 2027 flight schedule, while 10 preferred to make the transfer in summer 2028 or later.

The airlines said the move would require considerable preparation, including adjustments to flight networks and schedules, aircraft allocation, crew arrangements, and changes to ticketing and operational systems.

They would also need to establish offices, arrange ground-handling services and coordinate with relevant authorities to obtain the necessary approvals before starting operations at the new airport.

These preparations are particularly important for international airlines based overseas, which must coordinate their plans with aviation authorities in their home countries.

Cargo operators face additional requirements. International logistics companies, including UPS, FedEx and DHL, need suitable cargo terminals, customs facilities, aircraft parking positions and road connections to handle shipments efficiently.

The development comes as Long Thành International Airport prepares to begin commercial operations on December 24, 2026.

The airport, about 40km east of HCM City, is being developed in phases. Its first phase is designed to handle 25 million passengers and 1.2 million tonnes of cargo annually.

Long Thành is expected to take over a significant share of Tân Sơn Nhất’s international traffic, with the transfer taking place in stages rather than all at once.

However, airlines have also raised concerns about transport connections between Long Thành airport and HCM City, as well as the availability of passenger services, including transit hotels and healthcare facilities.

These services are important for international passengers, particularly those connecting between flights or travelling to and from the city.

Airport readiness under scrutiny

The ministry’s report also noted the importance of the airport’s operational readiness and airport transfer (ORAT) programme, which involves testing facilities, equipment, systems and procedures before commercial operations begin.

The programme comprises 55 scenarios and is divided into three phases scheduled between September and December 2026.

Integrated operational testing began in late September. However, the report noted that the period available for testing before the planned opening was relatively short.

It also said that no actual flights had been conducted as part of the integrated testing at the time covered by the report.

Operational testing is essential to identify problems involving passenger flows, baggage handling, aircraft movements and coordination among airlines, airport operators and service providers.

The ministry cited airport projects in Beijing, Istanbul and Hong Kong, where preparations and operational tests were carried out before commercial operations began or flights were transferred.

Such preparations can take several months, particularly at large airports with complex systems and multiple service providers.

The airlines’ proposals do not necessarily mean that Long Thành will miss its planned opening date. The airport could begin commercial operations as scheduled while international carriers gradually transfer their services over a longer period.

Long Thành, one of Việt Nam’s largest infrastructure projects, is expected to handle a significant share of HCM City’s international flights and expand the country’s aviation capacity. — VNS